August 2008 till November 2012
Construction Manager (Civil, Piping, Mechanical, E&I) for Entrepose Contracting (EPC) & Entrepose Projets (EPC) on the New LNG Train Skikda Project – Field Erected Tanks (KBR, SONATRACH), Algeria (one LNG tank 150000 m3 as per API 620, 2 LPG tanks 66000 m3 as per API 620, one Sphere 3000m3 as per ASME VIII DIV. 1 (‘U’ Stamp) and 6 API 650 tanks). Implementation and follow up of Quality and HSE management System, including coordination of construction activities inside the Consortium entity link to Civil works and all activities link to scheduling, coordination, follow up and in-house manpower management (400 numbers of national and expatriate personnel at peek) for Mechanical, Piping and E&I construction and pre-commissioning activities and system completion till Ready for Cool Down of the LNG and LPG tanks.